Get Involved      Careers      FAQ     Contact Us  
About Crystal Bridges

Construction Photos

Construction Site, April 2008. Despite record rainfalls this spring, work on the piers and foundations of the museum buildings continues at a fast pace. Visible in the middle foreground is the mat footing of the dining bridge’s east buttress. The grade beam on the east clearly defines the shapes of the museum store and administration building.

Photo by Brad Higbee, Eagle Eye Photography
March-April 2008
Overview looking east. This photo was taken from the temporary exhibitions gallery on the west side of the construction site; it shows the various levels of the museum complex. The construction workers in the foreground are walking on what will eventually become the bottom of the reflection pools.

Photo Courtesy of Liz Workman
March-April 2008
Milestone – First Major Pour Saint Patrick’s Day 2008 marks the first major pour on the construction site – the east buttress of the dining pavilion bridge.

Photo Courtesy of Liz Workman
March-April 2008
Teamwork. . Successfully orchestrating a major pour requires teamwork and precision. Concrete trucks moved from the construction yard batch plant to the site of the pour in a continuous stream for four hours. In all, 270 cubic yards of concrete were placed.

Photo Courtesy of Liz Workman
March-April 2008
Micro Piles. Work continues steadily on the installation of the museum’s 1,200 micro piles. These micro piles are a critical part of the museum’s foundation structure. They will provide resistance to the forces of the soil backfilled behind many of the buildings’ exterior walls. In the background, soil nailing with shot-crete is taking place along the western perimeter of the museum’s temporary exhibitions pavilion.

Photo Courtesy of Liz Workman
March-April 2008
Footing Excavation. Crews continue to excavate the rock for the footings of the perimeter retaining walls of the upper reflection pool along the administration building.

Photo Courtesy of Liz Workman
March-April 2008
Another Milestone – First structural shear wall to be poured. This foundation wall along gridline B18 in the administration building marks another first in the construction project. The shear wall will distribute lateral loads that are placed on the building’s perimeter by backfill.

Photo Courtesy of Liz Workman
March-April 2008
Parking Deck. Piers are now installed for the parking deck. In the background, the building where all of the concrete forms for the building project will be assembled has also been completed.

Photo Courtesy of Liz Workman
March-April 2008

Model Photos

View from the North
Copyright John Horner
View from the North
Copyright John Horner
View from the Northwest
Copyright John Horner
View from the Northwest
Copyright John Horner
Top aerial view left to right - North to South
Copyright John Horner
Top aerial view left to right - North to South
Copyright John Horner
View from the Southwest
Copyright John Horner
View from the Southwest
Copyright John Horner
View from the Northwest
Copyright John Horner
View from the Northwest
Copyright John Horner
View from the Upstream
Copyright John Horner
View from Upstream
Copyright John Horner

Perspective Photos
View from within the temporary exhibitions building (along the lower pond)
Copyright Moshe Safdie and Associates, Inc.
View from within the temporary exhibitions building (along the lower pond)
Copyright Moshe Safdie and Associates, Inc.
Copyright Moshe Safdie and Associates, Inc.
Copyright Moshe Safdie and Associates, Inc.
View from the visitor orientation area to the lower pond
Copyright Moshe Safdie and Associates, Inc.
View from the visitor's orientation area to the lower pond
Copyright Moshe Safdie and Associates, Inc..
View from outside the temporary exhibitions building
Copyright Moshe Safdie and Associates, Inc.
View from outside the temporary exhibitions building
Copyright Moshe Safdie and Associates, Inc.
Copyright Moshe Safdie and Associates, Inc.
View from outside the temporary exhibitions building
Copyright Moshe Safdie and Associates, Inc.

Building Plans
Copyright Moshe Safdie and Associates, Inc.
Copyright Moshe Safdie and Associates, Inc.
Copyright Moshe Safdie and Associates, Inc.
Copyright Moshe Safdie and Associates, Inc.
Context Site Plan
Copyright Moshe Safdie and Associates, Inc.

Context Site Plan
Copyright Moshe Safdie and Associates, Inc.


SEP
12
Goldilocks and the Three Bears
Friday, 2008 09:25 AM

SEP
10
Bears in the Woods
Wednesday, 2008 02:32 PM

AUG
11
Meet Amy Allen, Our Library Intern
Monday, 2008 08:25 AM

JUL
14
Crystal Bridges Staff Visits Site
Monday, 2008 10:04 AM

View All

SEP
10
Group of Bears Graces Compton Gardens
Wednesday, 2008 03:56 PM

SEP
04
The Indian and the Lily to be Display...
Thursday, 2008 04:14 PM

AUG
01
Noted Illustrator Brings Children’s B...
Friday, 2008 10:58 AM

MAY
15
Crystal Bridges at the Massey Hosts R...
Thursday, 2008 01:57 PM

View All
Get Involved     Careers     FAQ     Legal     Contact Us
Web Services by Rockfish Interactive